FuturGas Project Program
(quarters/dates are subject to change**)

**Q4, 2008

Completion of Groundwater Modelling for Pre-Feasibility Study

26 Nov 2008 Community Consultation Group - Initial Meeting
27 Nov 2008 Community Information Day, Lacepede Bay Motel, Kingston SE, 11.30am to 9.00pm
Q4, 2008 Joint Venture Agreement for FuturGas Geosequestration
**Q2, 2009 Completion of Pre-Feasibility (including Groundwater) Study
**Q2, 2009 Identification of Initial Land Requirement and Preliminary Discussions with Landowners
20 to 21 March 2009 Hybrid Energy Australia Community Information Days at the South East Field Days, Lucindale
**Q3, 2009 Consideration of Initial Land Purchase and Land Lease Options
**Q3, 2009 Commencement of Environmental Impact Statement (EIS) Preparation
Q3, 2010 Commencement of Semi-Industrial Scale Gasification Testing
Q4, 2010 Commencement of Pilot Groundwater Pumping and Re-Injection Trials
2010 Geological Formation Review for Geosequestration
**Q2, 2011 Completion of Feasibility studies
**Q3, 2011 Environmental Impact Statement (EIS) Final Report
**Q2, 2014 Commencement of Civil Works and Construction
**Q2, 2015 Commencement of Full Mine Overburden Operation
**Q2, 2016 Completion of Major CTL Plant Construction
Q2, 2016 Selection of Geosequestration Site and Final Pipeline Routes
Q2, 2016 Drilling of Geosequestration Wells
Q2, 2016 Commissioning of Plant Operation