**Q4, 2008 |
Completion of Groundwater Modelling for Pre-Feasibility Study |
| 26 Nov 2008 |
Community Consultation Group - Initial Meeting |
| 27 Nov 2008 |
Community Information Day, Lacepede Bay Motel, Kingston SE, 11.30am to 9.00pm |
| Q4, 2008 |
Joint Venture Agreement for FuturGas Geosequestration |
| **Q2, 2009 |
Completion of Pre-Feasibility (including Groundwater) Study |
| **Q2, 2009 |
Identification of Initial Land Requirement and Preliminary Discussions with Landowners |
| 20 to 21 March 2009 |
Hybrid Energy Australia Community Information Days at the South East Field Days, Lucindale |
| **Q3, 2009 |
Consideration of Initial Land Purchase and Land Lease Options |
| **Q3, 2009 |
Commencement of Environmental Impact Statement (EIS) Preparation |
| Q3, 2010 |
Commencement of Semi-Industrial Scale Gasification Testing |
| Q4, 2010 |
Commencement of Pilot Groundwater Pumping and Re-Injection Trials |
| 2010 |
Geological Formation Review for Geosequestration |
| **Q2, 2011 |
Completion of Feasibility studies |
| **Q3, 2011 |
Environmental Impact Statement (EIS) Final Report |
| **Q2, 2014 |
Commencement of Civil Works and Construction |
| **Q2, 2015 |
Commencement of Full Mine Overburden Operation |
| **Q2, 2016 |
Completion of Major CTL Plant Construction |
| Q2, 2016 |
Selection of Geosequestration Site and Final Pipeline Routes |
| Q2, 2016 |
Drilling of Geosequestration Wells |
| Q2, 2016 |
Commissioning of Plant Operation |